Project Description

Construction of concrete pipe racks with height of 16 meters and construction of industrial control room and substation buildings for development project of Isfahan refinery during six months including:

Casting: 21,000 cubic meters

Reinforcement: 840 tons Installation of buried metal parts

anchor bolt and anchor box: 70 tons

Concrete casting; 6,000 cubic meters

Project Details

  • Employer : Oil Design and Construction Company Design (ODCC)
  • Project Management : Sabz Ashiyan apadana Engineering Company
  • Status : Full Delivery